WELSHPOOL TOWN COUNCIL
PLANNING AND DEVELOPMENT COMMITTEE
MINUTES
Of a meeting held on Wednesday 14th December 2011 at 6pm
in the Assembly Room Town Hall Welshpool
Committee
Cllr E Bleivas, Cllr G Cross, Cllr A Crowe, Cllr H Evans, Cllr P Humphreys, Cllr S Kaye, Cllr J Meredith, Cllr Dr J Morgan, Cllr S Squibb and Cllr T Squibb.
Remit
All matters relating to planning, development, highways, planning applications, notices, regeneration, Motte and Bailey and the Town Centre.
Authority
To deal with the above without further reference to the Full Council except where the scheme is of a larger or sensitive nature.
Present were:
Cllr J Meredith (Chair), Cllr E Bleivas, Cllr G Cross, Cllr A Crowe and Cllr H Evans.
In attendance: Cllr T Harvey, Cllr P Pritchard, Cllr A Holloway and Robert Robinson Town Clerk.
1. Apologies for absence.
Apologies for absence were received from Cllr S Kaye, Cllr Dr J Morgan, Cllr S Squibb and Cllr T Squibb.
2. Minutes of the last meeting
The minutes of the last meeting were accepted as a correct record.
3. Gungrog Road Parking
The Town Council has been asked to give its views with regard to local resident’s requests for a change in the arrangements in Gungrog Road between Salop Road and the crossroads.
A local resident addressed the committee on the issues which revolve around the changes made some time ago which removed car parking and created the current situation.
The Town Council considered
a potential scheme involving a one way street proposal. Details of what was
considered are in the file with the agenda papers.
The traffic during the daytime is very low but the traffic on a weekend day is
busy. The current parking restrictions do not appear to take this into account.
The Committee was consulted by PCC and the Committee voted on various alternative arrangements as follows:
The idea of a one way system. Not supported.
The removal of daytime restrictions on parking. Supported.
The introduction of a parking permit scheme. Supported.
4. Planning decisions
A number of planning decisions were read out by the Chair.
Cllr G Cross had to leave at this point in the meeting.
5. Town Centre developments
a) One way system
The Town Clerk confirmed
that a Zebra Crossing is being provided by the Town Hall and should be in place
by March 2012.
The Town Clerk pointed out a concern that a Zebra Crossing may not be totally
effective on busy days with people crossing in numbers with the traffic flows.
The WAG Highways Engineers are of the view that the proposal will work but will keep it under review when it has been installed.
The signage still required is still being followed up.
Cllr P Pritchard recorded his views as per the attached paper to these minutes.
The Committee AGREED that their views on the crossing by the Town Hall be communicated to the WAG as follows:
The Committee is grateful that a crossing point is being provided.
The Committee had concerns over the effectiveness of a Zebra Crossing.
The Committee had concerns over the effectiveness of a Pelican unless linked with the Cross traffic lights.
The Committee felt a single lane with narrow crossing areas would be better.
b) Church Street car park scheme
A letter which has been received from J Ross Developments together with a memo from John Pearson (PCC Planning Dept) was circulated to all Councillors before the meeting.
J Ross Developments are seeking for guidance from the Town Council with regard to what scheme, if any, they would be prepared to support on the site.
The Committee was advised that this was not a planning application and that only an informal approach has been made.
The principle of development to form a retail use is acceptable in principle to PCC.
The applicant is to be asked to submit the extended application to PCC so that a re-consultation takes place. This will give time for the Council to formally consult with the public on the principles.
A request was made that lorries should be allowed to park in the Coach bays proposed at night when they are not in use.
A paper by Cllr Dr J Morgan was circulated and is on file with the agenda papers.
RECOMMENDATION
The Committee RECOMMENDS that which such an important decision to the Town that a public consultation should be held on the first Tuesday in January from 9am till 9pm in the Corn Exchange seeking public opinion so that the Council has a clear indication as to the way the public wish to see any response from the Town Council to the next Planning Application consultation.
The cost of such consultation is some photocopying.
c) Puzzle Square
The members were given a copy of a letter from Colin Edwards at PCC regarding the license approval following the letter to him from the Town Clerk as per the instructions of the Committee at its last meeting. (See file for details). The Town Clerk is to request that in any future licensing grants include the provision for a CCTV camera to be linked to the Town System.
6. Planning applications
P2011 1305 Lower Coed y Lade Farm Trelydan
Erection of a 2 storey rear extension.
The Committee SUPPORTS this application.
P2011 1321 Tan House Coppice Lane Pool Quay
Construction of an all weather mange.
The Committee SUPPORTS this application.
P2011 1323 Land opposite The Moors Farm Buttington
Erection of an agricultural building and hard standing.
The Committee SUPPORTS this application.
TREE2011/0039 22 Heulwen Way
Reduction of 3 silver birch trees together and removal of one silver birch tree protected by TPO 67A.
The Committee SUPPORTS this application.
P2011 1360 Garden Nursery at Powis Castle
Installation and operation of a ground mounted array of 150 solar PV panels with associated inverters and cabling.
The Committee SUPPORTS this application.
P2011 1377 Waterloo Rovers Maes Y Dre
The planning application for an extension to the changing rooms at Maes Y Dre by
Waterloo Rovers was discussed.
The Committee SUPPORTS the application but wishes to point out to Powys
County Council that the Council has an interest in the land by virtue of being
the freeholder of the site.
7. Motte and Bailey
The Motte and Bailey scheme has now been drafted in site plan form.
There is to be a final project meeting in January 2012 to finalise the plan which will go forward.
A decision will be sought in January regarding the lease arrangements to be put in place.
8. Local Development Plan – candidate sites
The list of candidate sites has been published in advance of any plan being formally prepared.
The full list will be available at the next meeting for members to see.